Project Description

Project:   Cleveland High School
Location: Portland, OR
Surface Area: 175,589sf
Year Completed: 2017
Value: $6,200,000
Architect: Oh Planning & Design

Work included re-roofing of the main school building with SBS roofing materials and rigid insulation, replace skylights and roof hatches, replace gutters and downspouts, raise weeps in existing brick cavity walls to accommodate new roof level, fill in existing roof access door and install new roof over access well, replace existing ladder and add new roof ladders, raise existing window and door sills to accommodate new roof level, replace windows and doors, raise parapets and perimeter walls of some roofs to accommodate new roof level, remove brick chimney, install new ADA compliant handrails, install new ADA compliant lever handles on doors.