Junction City High School

Project Description

Project:   Junction City High School
Location: Junction City, OR
Surface Area: 37,000sf
Year Completed: 2019
Value: $14,000,000
Architect: DLR Group

Construction of a new 37,000 square foot, 2-story classroom addition including new science classrooms, computer lab and media center.  In additional a new reception area, office spaces and work room as well as a community and digital arts room are being constructed.   Concurrent with the new addition a renovation of approximately 12,000 square feet of existing school space will be completed. Associated site improvements including a large outdoor concrete plaza with terraced seated walls, parking, hardscape, landscape, and utility work.

Washington County Public Safety Training Center

Subcontractors

Project Documents

Project Description

Project:   Washington County Public Safety Training Center
Location: Hillsboro, OR
Surface Area: 116,029sf
Year Completed: July 2019
Value: $12,700,000
Architect: Scott Edwards Architecture

The Washington County Public Safety Training Center project located in Hillsboro, Oregon consists of complete renovation to an existing 2-story, Type 5-B, fully sprinkled building.  The addition of a second floor within the existing building, a small building addition and all associated site improvements. The completed facility will include office/administration spaces, training classrooms, shooting range, and an armory.

Oak Grove Elementary

Project Description

Project:   Oak Grove School
Location: Portland, OR
Surface Area:
Year Completed: 2018
Value: $2,855,000
Architect: BBL Architects

Renovation of existing Oak Grove Elementary School including Kitchen renovation, interior painting, replace carpet and base in (10) Classrooms, new door hardware, removal and replacement of existing roof and sheet metal over western most Classroom area.  Replace existing glazing with insulated glazing units with new window blinds at select Classrooms, and Administrative Offices. There will also be partial lighting upgrades in the hallways, new fire panel and detection equipment, ,new HVAC unit(s) and controls at select Classrooms.

New Maintenance Facility

Project Description

Project:   New Maintenance Facility
Location: Vancouver, WA
Surface Area:
Year Completed: 2012
Value: $4,100,000
Architect: LSW Architects

Construction of a new maintenance facility.

Fire Station 92

Project Description

Project:   Fire Station 92
Location: Mercer Island, WA
Surface Area:
Year Completed: 2013
Value: $3,600,000
Architect: Miller Hull Partnership LLP

May Valley Rd Fire Station 78

Project Description

Project:   May Valley Rd Fire Station 78
Location: Issaquah, WA
Surface Area: 9,500sf
Year Completed: 2014
Value: $4,2000,000
Architect: TCA Architecture

Single story building of approximately 9,500 square feet that houses fire station personnel with three (3) drive through vehicle bays and crew living and sleeping and office areas. Composite asphalt shingle roofing, aluminum storefront, overhead doors, fiber cement panel siding and horizontal fiber cement board siding exterior, interior finishes, mechanical, plumbing, fire protection and electrical. The project also included the development of the approximately 2 acres of a 5.79 acre project site which involved site clearing, retaining structures, concrete and asphalt paving, construction of site and frontage improvements and off-site improvements.

Hood River Fire Station

Project Description

Project:   Hood River Fire Station
Location: Hood River, OR
Surface Area:
Year Completed: 2012
Value: $3,300,000
Architect: Group Mackenzie

This project began with the demolition of the existing Fire Station structure and related site work necessary to prepare for the new building. The new, 2-story Fire Station is comprised of approximately 17,900 square feet. It is a wood framed structure with masonry veneer, fiber cement board siding, and aluminum storefront windows. Seismic rehabilitation was also completed. This was a 10 month project.

Clark College Stout Hall

Project Description

Project:   Clark College Stout Hall
Location: Vancouver, WA
Surface Area:
Year Completed: 2006
Value: $3,700,000
Architect: LSW Architects

This project began with the demolition of the existing Stout Hall structure which housed classrooms, study areas and concessions. The new unique curved structure ties to existing buildings on two sides and is the anchor of the southeast corner of the main campus. The multi-level steel framed structure features 10 smart classrooms, 20 faculty offices, a student lounge and a food vending area. Extensive underground work was necessary to house piping for site utilities, electric power and storm drainage.

Camas High School

Project Description

Project:   Camas High School
Location: Camas, WA
Surface Area: 25,000sf
Year Completed: 2011
Value: $6,600,000
Architect: Dull Olson Weeks Arch PC

The Camas High School project consisted of renovations and an addition of approximately 25,000 square feet that increased the school’s capacity by 350 students. The project included a new student commons, training classroom, wrestling and dance rooms and classroom wing, which adds the equivalent of 11 classrooms. The library was also expanded and the physical education areas renovated. Additionally, the front entrance of the school was renovated to help improve security.

Marysville K-8 Rebuild

Project Description

Project:   Marysville K-8 Rebuild
Location: Portland, OR
Surface Area: 124,768sf
Year Completed: 2012
Value: $4,100,000
Architect: DLR Group

Restoration of an existing 53,490 square foot, single story, wood frame structure, rebuild of burned gymnasium, classroom upgrade to science lab, conversion of unburned gymnasium to media center, creation of new tech lab/classroom and reconfiguration of existing admin area.